Swiss federal authorities

Expert reports

3 documents
3 documents found. You are viewing page 1 from 1 pages.
  • Expert report on the Supplementary Diorit Decommissioning Project of the Paul Scherrer Institute
    News, Posts

    Supplementary Diorit decommissioning project at PSI meets protection objectives

    PSI has clearly demonstrated that the supplementary decommissioning project of the Diorit nuclear installation can comply with the basic protection objectives of nuclear safety and security. This is the conclusion reached by ENSI in its expert report.

  • Expert report on the Supplementary Diorit Decommissioning Project of the Paul Scherrer Institute

    Expert Report on the Supplementary Diorit Decommissioning Project of the Paul Scherrer Institute

    The Paul Scherrer Institute (PSI) has clearly demonstrated in its documentation for the supplementary decommissioning of the Diorit nuclear installation that the basic protection objectives of nuclear safety and security can be met. This is recorded in ENSI’s expert report.

  • Assessment of the Safety Case for the Reactor Pressure Vessel of the Beznau Unit 1 Nuclear Power Plant

    The IRP considers that the Axpo Safety Case is acceptable. This is based on the following: